Sr. No. |
Description of Milestones |
Target date |
Status as on 31.12.2011 |
|
1 |
Submission of Application for Forest Clearance |
30.06.11 |
As per Nepal Law of Land, submission of application for Forest clearance from MEF /GON is only possible after clearance of EIA/EMP,IEE reports. However application was submitted on 29.09.2011. |
|
2 |
Environment clearance (IEE) for road from Kuanpani to Num, Num to Dam site & Chainkutty to Diding(PH) from GON |
30.06.11 |
The IEE for road from Chainkutty to Diding (PH) cleared by Secretary, GON on 29.09.11 and the formal order has been issued on 10/10/2011.
Kuanpani to Num- IEE report is under clearance with MoE. |
|
3. |
Completion of Socio-economic Survey (SES) and Social Impact Assessment (SIA) Studies |
31.10.10 |
WAPCOS to take up work after TOR approval. Field work completed. |
|
4. |
Completion of Survey Works for identification of land for Infrastructure works. |
15.12.2011 |
Work completed on 30.11.11. |
|
5. |
Submission of EIA/EMP studies and R&R report to GON |
31.12.11 |
The Improved version of Scoping document / TOR has been re-submitted to Ministry of Environment on 22/09/2011 with a request for early clearance of report. |
|
6. |
Submission of Land Details to GON for acquisition |
15.03.12 |
Possession of land has been given to SJVN. |
|
7. |
Construction of Temporary Causeway on Sabha Khola and Award for Balley
bridge for Kagna Khola Bridge |
31.03.2012 |
The single tender received against open tender enquiry was opened on 15.12.2011 after taking the approval of Director (E) . The tender has to be cancelled due to not submitting EMD by the only bidder required as per tender document. however, the construction of bridge is in progress by GON . |