The project is located between Nandkeshri Bridge and Simli Gad in Tehsil
Tharali, Distt. Chamoli of Uttarakhand State between Latitude 30°02’35”-
30°07’30”N and Longitude79°34’17”- 79°25’00”E Present Status of Devsari HE PROJECT
Implementation Agreement for the execution of 300 MW Devsari HEP has been
signed between Satluj Jal Vidut Nigam Limited and Govt. of Uttarakhand on
November 21, 2005. The storage Dam (Devsari HEP-300MW) has been converted
into Run of the River Scheme as Devsari HEP Stage-I 252 MW on 04/10/2007
and agreed by Govt. of Uttarakhand between elevation of 1300m and 1045m on
Pinder river. Preliminary Survey and Investigation works has been completed
and is in process for TEC.
The revised DPR was submitted to CEA on 29.6.10. EIA/EMP report after in corporating public hearing consultation data submitted to MoEF on 01.03.2011 and the matter is with EAC of MoEF for clearence.
Completion of Devsari HE PROJECT
The 252 MW Devsari HE Project is expected to be commissioned in XIIth Plan.
PROJECT COST
On completion, the cost of project is estimated at Rs. 1357.75 Crores at
June 2010 price level as per the DPR submitted to CEA.
Project Benefits
Besides the social and economic upliftment of the people in its vicinity, the
252 MW Devsari Hydro Electric Project will generate 910.16 GWh of electrical
energy in a 90% dependable year.
|