Sr. No. |
Description of Milestone |
Target date |
Status as on 31.12.2011 |
|
1 |
Obtaining Environment Clearance from MoEF |
31.07.10 |
EAC meeting held successfully on 27.12.11. Minutes of meeting awaited. |
|
2 |
Submission of documents to MoEF for Forest Clearance |
30.09.11 |
The complete case for forest land diversion was forwarded by DFO to CF, Pauri on 17.12.11. CF, Pauri returned back the case files to DFO on 28.12.11 and asked DM, Chamoli to issue a certificate regarding the status of Civil Forest Land whether it is forest or non forest land with regards to latest Govt. order issued by GoUK. |
|
3 |
Section 6 notification for Private land acquisition |
31.07.10 |
All 16 case have been submitted by SLAO to Secretary (Energy), GoUk for declaration under Section 6. Being followed up. Section 6 notification for 5 cases has been issued. |
|
4 |
TEC |
30.09.10 |
DPR submitted to CEA on 29.06.10. CEA Standing Committee meeting held on 14.11.11 in which some observations were raised by the committee. Reply to the observations are being prepared. TEC possible after clearance by Standing Committee. |