Sr. No. |
Description of Milestone |
Target date |
Status as on 30.04.12 |
|
1. |
Award of work for construction of abutments of two no. bailey bridges |
31.08.12 |
Presentation has been made to CEA on 29.07.11. TEC awaited. |
|
2. |
Award of work for supply and erection of two no. of bailey bridges |
30.09.12 |
|
|
3 |
Award of work for Project roads |
30.11.12 |
|
|
4. |
Award of work for construction of all adits to HRT |
28.02.13 |
|