Sr. No.

Description of Milestone

Target date

Status as on 30.04.12

1. Award of work for construction of abutments of two no. bailey bridges 31.08.12 Presentation has been made to CEA on 29.07.11. TEC awaited.
2. Award of work for supply and erection of two no. of bailey bridges 30.09.12  
3 Award of work for Project roads 30.11.12  
4. Award of work for construction of all adits to HRT 28.02.13  

 

   
 