SJVN LIMITED
NATHPA JHAKRI HYDROELECTRIC POWER STATION

Total Power Generated Till Dated 10.04.10 is 36216.651 MU
Year 2010-2011 

DAILY GENERATION  REPORT FOR 10.04.10

GENERATION (MU) 

DAILY

MONTHLY Cuml.

YEARLY Cuml.

 

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

 

 

 

 

 

 

 

 

 

 

  

 

 

9.255

12.500

13.037

12.934

92.550

100.394

103.862

103.129

92.550

100.394

103.862

103.129

 

 

 

 

 

 

 

 

 

 

Unit No.

Daily (MU)

Running Hours 

Planned Outage

Forced Outage due to break down in M/C

Misc.

Availability 

Remarks

High    PPM/RED

ALERT

Less Avail. of Water

Grid Constraints ETC.

 

Gross

Ex-Bus

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

 

Unit - 1 

0.786

0.778

3:26

0:00:00

0:00:00

0:00

20:34

0:00:00

24:00

Unit - 2 

0.868

0.861

3:26

0:00:00

0:00:00

0:00

20:34

0:00:00

24:00

Unit - 3 

2.063

2.043

8:55

0:00:00

0:00:00

0:00

15:05

0:00:00

24:00

Unit - 4 

2.985

2.974

12:57

0:00:00

0:00:00

0:00

11:03

0:00:00

24:30

Unit - 5 

4.590

4.542

19:58

0:00:00

0:00:00

0:00

4:02

0:00:00

24:00

Unit - 6 

1.745

1.736

7:45

0:00:00

0:00:00

0:00

16:15

0:00:00

24:00

 

Total

13.037

12.934

56:27

0:00:00

0:00:00

0:00

87:33

0:00:00

144:00

   

HYDROLOGICAL DATA

Discharge for Generation (Cumecs)
Satluj and Sholding 

Level (Meters)

SILT (PPM)

Inflow for Generation

137

Max. Dam Level

1495.25

 

Max.

at (Hr.Min)

Min.

at(Hr.Min)

Water Utilized

136

Min. Dam Level

1479.70

Wangtoo

432

19:00

371

1:00

Water Spillage

-

Max. TRT Level

N/A

SFT

N/A

N/A

N/A

N/A

Water utilised for SFT flushing

-

Min. TRT Level

N/A

Draft Tube

196

22:00

95

9:00

 

Coarse Silt Particles

-

Max.

Min.

Dam

10

0

Draft Tube

2

0