SJVN LIMITED
NATHPA JHAKRI HYDROELECTRIC POWER STATION

Total Power Generated Till Dated 15.04.10 is 36285.646 MU
Year 2010-2011 

DAILY GENERATION  REPORT FOR 15.04.10

GENERATION (MU) 

DAILY

MONTHLY Cuml.

YEARLY Cuml.

 

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

 

 

 

 

 

 

 

 

 

 

  

 

 

11.387

12.750

13.010

12.908

149.485

170.572

172.857

171.499

149.485

170.572

172.857

171.499

 

 

 

 

 

 

 

 

 

 

Unit No.

Daily (MU)

Running Hours 

Planned Outage

Forced Outage due to break down in M/C

Misc.

Availability 

Remarks

High    PPM/RED

ALERT

Less Avail. of Water

Grid Constraints ETC.

 

Gross

Ex-Bus

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

 

Unit - 1 

1.314

1.306

5:42

0:00:00

0:00:00

0:00

18:18

0:00:00

24:00

Unit - 2 

2.334

2.312

10:17

0:00:00

0:00:00

0:00

13:43

0:00:00

24:00

Unit - 3 

3.228

3.200

13:24

0:00:00

0:00:00

0:00

10:36

0:00:00

24:00

Unit - 4 

1.238

1.232

4:58

0:00:00

0:00:00

0:00

19:02

0:00:00

24:30

Unit - 5 

2.299

2.275

9:04

0:00:00

0:00:00

0:00

14:56

0:00:00

24:00

Unit - 6 

2.597

2.583

10:23

0:00:00

0:00:00

0:00

13:37

0:00:00

24:00

 

Total

13.010

12.908

53:48

0:00:00

0:00:00

0:00

90:12

0:00:00

144:00

   

HYDROLOGICAL DATA

Discharge for Generation (Cumecs)
Satluj and Sholding 

Level (Meters)

SILT (PPM)

Inflow for Generation

137

Max. Dam Level

1493.05

 

Max.

at (Hr.Min)

Min.

at(Hr.Min)

Water Utilized

136

Min. Dam Level

1476.70

Wangtoo

464

19:00

406

7:00

Water Spillage

-

Max. TRT Level

N/A

SFT

N/A

N/A

N/A

N/A

Water utilised for SFT flushing

-

Min. TRT Level

N/A

Draft Tube

137

23:00

70

16:00

 

Coarse Silt Particles

-

Max.

Min.

Dam

10

0

Draft Tube

4

0