SJVN LIMITED
NATHPA JHAKRI HYDROELECTRIC POWER STATION
Total Power
Generated Till Dated 21.04.10 is 36391.455 MU
Year 2010-2011
DAILY GENERATION REPORT FOR 21.04.10
GENERATION
(MU)
|
DAILY |
MONTHLY Cuml. |
YEARLY Cuml. |
| ||||||||||||||
|
MOU Gross Target |
Schedule Target (Ex-Bus) |
Gross Achieved |
Ex-Bus Achieved |
MOU Gross Target |
Schedule Target (Ex-Bus) |
Gross Achieved |
Ex-Bus Achieved |
MOU Gross Target |
Schedule Target (Ex-Bus) |
Gross Achieved |
Ex-Bus Achieved |
| |||||
|
|
|
|
|
|
|
|
|
|
|
|
| ||||||
|
14.661 |
18.591 |
20.159 |
19.984 |
221.081 |
273.513 |
278.666 |
276.445 |
221.081 |
273.513 |
278.666 |
276.445 | ||||||
|
|
|
|
|
|
|
|
|
|
| ||||||||
|
Unit No. |
Daily (MU) |
Running Hours |
Planned Outage |
Forced Outage due to break down in M/C |
Misc. |
Availability |
Remarks | ||||||||||
|
High PPM/RED ALERT |
Less Avail. of Water |
Grid Constraints ETC. | |||||||||||||||
|
|
Gross |
Ex-Bus |
Hr:Min. |
Hr:Min. |
Hr:Min. |
Hr:Min. |
Hr:Min. |
Hr:Min. |
Hr:Min. |
| |||||||
|
Unit - 1 |
5.203 |
5.145 |
21:22 |
0:00:00 |
0:00:00 |
0:00 |
2:38 |
0:00:00 |
24:00 | ||||||||
|
Unit - 2 |
4.565 |
4.527 |
18:29 |
0:00:00 |
0:00:00 |
0:00 |
5:31 |
0:00:00 |
24:00 | ||||||||
|
Unit - 3 |
4.268 |
4.227 |
17:16 |
0:00:00 |
0:00:00 |
0:00 |
6:44 |
0:00:00 |
24:00 | ||||||||
|
Unit - 4 |
4.023 |
4.001 |
16:41 |
0:00:00 |
0:00:00 |
0:00 |
7:19 |
0:00:00 |
24:30 | ||||||||
|
Unit - 5 |
2.100 |
2.084 |
8:38 |
0:00:00 |
0:00:00 |
0:00 |
15:22 |
0:00:00 |
24:00 | ||||||||
|
Unit - 6 |
0.000 |
0.000 |
0:00 |
0:00:00 |
0:00:00 |
0:00 |
24:00 |
0:00:00 |
24:00 | ||||||||
|
| |||||||||||||||||
|
Total |
20.159 |
19.984 |
82:26 |
0:00:00 |
0:00:00 |
0:00 |
61:34 |
0:00:00 |
144:00 | ||||||||
|
| |||||||||||||||||
|
HYDROLOGICAL DATA | |||||||||||||||||
|
Discharge
for Generation (Cumecs) |
Level (Meters) |
SILT (PPM) | |||||||||||||||
|
Inflow for Generation |
219 |
Max. Dam Level |
1495.50 |
|
Max. |
at (Hr.Min) |
Min. |
at(Hr.Min) | |||||||||
|
Water Utilized |
210 |
Min. Dam Level |
1481.00 |
Wangtoo |
1651 |
19:00 |
794 |
1:00 | |||||||||
|
Water Spillage |
- |
Max. TRT Level |
N/A |
SFT |
N/A |
N/A |
N/A |
N/A | |||||||||
|
Water utilised for SFT flushing |
- |
Min. TRT Level |
N/A |
Draft Tube |
901 |
23:00 |
455 |
1:00 | |||||||||
|
|
Coarse Silt Particles | ||||||||||||||||
|
- |
Max. |
Min. | |||||||||||||||
|
Dam |
18 |
0 | |||||||||||||||
|
Draft Tube |
8 |
2 | |||||||||||||||