SJVN LIMITED
NATHPA JHAKRI HYDROELECTRIC POWER STATION

Total Power Generated Till Dated 03.07.10 is 38648.574 MU
Year 2010-2011 

DAILY GENERATION  REPORT FOR 03.07.10

GENERATION (MU) 

DAILY

MONTHLY Cuml.

YEARLY Cuml.

 

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

 

 

 

 

 

 

 

 

 

 

  

 

 

35.149

36.752

37.167

36.841

105.447

109.936

111.213

110.235

2339.065

2514.906

2535.785

2514.698

 

 

 

 

 

 

 

 

 

 

Unit No.

Daily (MU)

Running Hours 

Planned Outage

Forced Outage due to break down in M/C

Misc.

Availability 

Remarks

High    PPM/RED

ALERT

Less Avail. of Water

Grid Constraints ETC.

 

Gross

Ex-Bus

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Unit - 1 

6.321

6.259

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 2 

6.226

6.175

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 3 

6.172

6.116

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 4 

6.272

6.227

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 5 

5.923

5.860

23:10

0:00:00

0:50:00

0:00

0:00

0:00:00

24:00

Unit - 6 

6.253

6.204

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

 

Total

37.167

36.841

143:10

0:00:00

0:50:00

0:00

0:00

0:00:00

144:00

   

HYDROLOGICAL DATA

Discharge for Generation (Cumecs)
Satluj and Sholding 

Level (Meters)

SILT (PPM)

Inflow for Generation

802

Max. Dam Level

1495.10

 

Max.

at (Hr.Min)

Min.

at(Hr.Min)

Water Utilized

387

Min. Dam Level

1493.00

Wangtoo

1857

22:00

1444

10:00

Water Spillage

-

Max. TRT Level

N/A

SFT

NA

NA

NA

NA

Water utilised for SFT flushing

-

Min. TRT Level

N/A

Draft Tube

1129

13:00

491

2:00

 

Coarse Silt Particles

-

Max.

Min.

Dam

0

0

Draft Tube

12

3