SJVN LIMITED
NATHPA JHAKRI HYDROELECTRIC POWER STATION

Total Power Generated Till Dated 25.03.10 is 36038.929 MU
Year 2009-2010 

DAILY GENERATION  REPORT FOR 25.03.10

GENERATION (MU) 

DAILY

MONTHLY Cuml.

YEARLY Cuml.

 

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

 

 

 

 

 

 

 

 

 

 

  

 

 

8.246

12.390

12.209

12.144

183.880

217.363

221.509

219.418

6451.294

6881.457

6944.398

6882.989

 

 

 

 

 

 

 

 

 

 

Unit No.

Daily (MU)

Running Hours 

Planned Outage

Forced Outage due to break down in M/C

Misc.

Availability 

Remarks

High    PPM/RED

ALERT

Less Avail. of Water

Grid Constraints ETC.

 

Gross

Ex-Bus

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

 

Unit - 1 

1.306

1.298

5:19

0:00:00

0:00:00

0:00

18:41

0:00:00

24:00

Unit - 2 

3.734

3.719

16:47

0:00:00

0:00:00

0:00

7:13

0:00:00

24:00

Unit - 3 

0.189

0.188

0:46

0:00:00

0:00:00

0:00

23:14

0:00:00

24:30

Unit - 4 

3.264

3.252

13:01

0:00:00

0:00:00

0:00

10:59

0:00:00

24:30

Unit - 5 

2.326

2.302

10:11

0:00:00

0:00:00

0:00

13:49

0:00:00

24:00

Unit - 6 

1.390

1.385

5:41

0:00:00

0:00:00

0:00

18:19

0:00:00

24:00

 

Total

12.209

12.144

51:45

0:00:00

0:00:00

0:00

92:15

0:00:00

144:00

   

HYDROLOGICAL DATA

Discharge for Generation (Cumecs)
Satluj and Sholding 

Level (Meters)

SILT (PPM)

Inflow for Generation

130

Max. Dam Level

1495.00

 

Max.

at (Hr.Min)

Min.

at(Hr.Min)

Water Utilized

127

Min. Dam Level

1478.45

Wangtoo

438

19:00

361

12:00

Water Spillage

-

Max. TRT Level

N/A

SFT

N/A

N/A

N/A

N/A

Water utilised for SFT flushing

-

Min. TRT Level

N/A

Draft Tube

117

10:00

67

4:00

 

Coarse Silt Particles

-

Max.

Min.

Dam

0

0

Draft Tube

0

0